You finished the job. The client is happy. The quality is good.
Then the final account lands on your desk — and the margin isn’t there.
Nobody stole it. Nothing collapsed. It left quietly, one piece of paper at a time.
This is the first edition of a weekly note for people who build, and for the contract and commercial teams behind them. One idea. One thing to do. Three minutes.
The idea
Contractors don’t go bust on site. They go bust on paper.
Site problems are loud. A crane goes down and your phone rings within a minute.
Paper problems are silent. A missed notice makes no noise. An unpriced change sends no alert. A payment cut nobody challenged just becomes the new baseline.
“We build well, so we’ll get paid” feels right. Good work earns trust. Getting paid what the contract owes you also takes proof: showing your entitlement, following the agreed procedure, and doing it before the deadline passes.
On a live contract, money leaks in five places. The 5Cs Framework™ names a control for each:
- CONTAIN Scope & variations
- COMMAND Programme, delay & claims
- CLOSE Instructions & decisions
- CONFIRM Payments & certification
- CONTROL Deadlines & weekly review
If you have no contract team
The contract falls on your project manager, at 11pm, after everything else. Your project manager hasn’t failed. Nobody was given the time to do this job. You don’t need a department to start. You need one list, one owner and one fixed hour a week.
If you already have a strong team
Strong teams lose entitlement too, in peak months, when everyone moves to the urgent. Nobody dropped the ball. There were more balls than hands. Your team can do the work. In those months there’s just too much of it.
One thing to do this week
Pick your most exposed live contract. Block 60 minutes. Ask one question for each control:
- Can you list this month’s changes, and say which are priced?
- If a delay claim landed this Friday, could you show what happened, week by week?
- Which instructions and decisions are still open, who owns each one, and when must it be closed?
- Can you reconcile what you applied for, what was certified and what was paid, and explain every difference?
- Which notice deadlines fall in the next two weeks, and who owns each one?
“I don’t know” counts as a no. Put every no on one page: the item, one owner, one date. Book the same hour next week.
That hour is our recommended discipline, not a contractual deadline. For any notice date, check your contract’s own clause — editions, particular conditions and governing law change the consequences of a late notice.
Read the full article
Where each leak starts, and why the five feed each other. Read it or listen:
Also in the article library now: The 28-day clock: how a missed notice can put your claim at risk.